If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?
Given,
27 people working 8 hours a day can complete the task in 12 days
$$=$$>  $$M_1=27$$, $$d_1=12$$, $$h_1=8$$
Let 18 people working 9 hours a day can complete the task in $$d_2$$ days
$$=$$> Â $$M_2=18$$, Â $$h_2=9$$
Let the total work = W
we know that $$\frac{M_1\times d_1\times h_1}{W_1}=\frac{M_2\times d_2\times h_2}{W_2}$$
$$=$$> Â $$\frac{27\times12\times8}{W}=\frac{18\times d_2\times9}{W}$$
$$=$$> Â $$d_2=$$ 16 days
Hence, the correct answer is Option C