A and B together can finish a work in 20 days. If they worked together for 8 days, then what was the share of work that was yet to be completed?
A and B together can finish a work in 20 days. If they worked together for 8 days.
Then, together they need to work (20-8) = 12 days more to complete the work.
Share of work that was yet to be completed =Â $$\frac{12}{20}$$
=Â $$\frac{3}{5}$$
Another method
Let's assume the total work is 20 units.
A and B together can finish a work in 20 days.
The efficiency of A and B together = $$\frac{20}{20}$$ = 1unit/day
If they worked together for 8 days.
Work done by them in 8 days = $$8\times1$$ = 8 units
Remaining work = 20-8 = 12 units
Share of work that was yet to be completed = $$\frac{12}{20}$$
= $$\frac{3}{5}$$