Z1, Z2 and Z3 can do a work in 100, 50 and 75 days respectively. All three of them began the work together but Z2 left 15 days before the completion of the work. In how many days was the work completed?
40 days
45 days
30 days
35 days
Create a FREE account and get:
SSC Data Interpretation
SSC Geometry
SSC Linear Equations
SSC Number Systems
SSC Quadratic Equations
SSC Trigonometry
SSC Ages
SSC Arithmetic
SSC Reading Comprehension
SSC Vocabulary
SSC Analogy
SSC Coding Decoding
SSC Directions
SSC Meaningful Order
SSC Number Series
SSC Puzzles
SSC Syllogisms
SSC Words Formation
SSC Venn Diagram
Login to your Cracku account.
Enter Valid Email
Follow us on
Incase of any issue contact support@cracku.in
Boost your Prep!
Quick, Easy and Effective Revision
By proceeding you agree to create your account
Free CAT Formulae PDF will be sent to your email address soon !!!