Question 60

If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days?

Solution

$$M1\times D1\times H1=M2\times D2\times H2$$

$$40\times 8\times 12=M2\times 16\times 4$$

$$M2= 60 $$