Mandeep works 3 times as fast as Sampat. If Sampat can complete a job alone in 60 days, then in how many days can they together finish the job?
Let total work to be done = 60 units
Sampat can complete a job alone in 60 days
=> Sampat's efficiency = $$\frac{60}{60} = 1$$ unit/day
Also, Mandeep works 3 times as fast as Sampat
=> Mandeep's efficiency = $$3 \times 1=3$$ units/day
(Sampat+Mandeep)'s 1 day's work together = 1 + 3 = 4 units/day
$$\therefore$$ Time taken by them to finish the job together = $$\frac{60}{4} = 15$$ days
=> Ans - (D)