To do a certain work, the ratio of the efficiencies of A and B is 7:6. Working together, they can complete the same work in 21 days. What part of the same work will be completed by B alone in 26 days ?
$$\frac{5}{8}$$
$$\frac{4}{7}$$
$$\frac{5}{6}$$
$$\frac{2}{3}$$