Question 54

A, B, and C can complete a work in 15, 30, and 20 days respectively. A left the work 1 day before the work was completed and B left 2 days before the completion of the work. Find the number of days required to complete the whole work.


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App