Question 54

4 men, working together, can finish a work in 18 days. How many more men are required to finish the same work in 12 days?


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App