Question 53

12 men can weave 20 shawls in 9 days. How many men will be required to weave 25 shawls in 27 days?

12 men can weave 20 shawls in 9 days. How many men will be required to weave 25 shawls in 27 days?

$$\frac{men_{_1}\times\ days_{_1}}{work_{_1}}\ =\ \frac{men_{_2}\times\ days_{_2}}{work_{_2}}$$

$$\frac{12\times9}{20} = \frac{men_{_2}\times 27}{25}$$

$$\frac{108}{20} = \frac{men_{_2}\times 27}{25}$$

$$\frac{27}{5} = \frac{men_{_2}\times 27}{25}$$

$$men_{_2} = 5$$

So 5 men will be required to weave 25 shawls in 27 days.

Get AI Help

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

Join CAT 2026 course by 5-Time CAT 100%iler

Crack CAT 2026 & Other Exams with Cracku!

Ask AI

Ask our AI anything

AI can make mistakes. Please verify important information.