Question 51

P, Q and R can complete a work in 30 days, 15 days and 20 days respectively. P works on first day, then Q works on second day and then R works on third day and so on. In how many days the work will be completed?

Solution

Let the total work be 60 units (LCM of 30,15 and 20)
Efficiency of P = 60/30 = 2 units per day
Efficiency of Q = 60/15 = 4 units per day
Efficiency of R = 60/20 = 3 units per day
Then, 9 units of work will be completed in 3 days.
=> 54 units of work will be completed in 18 days.
Next 2 units of work will be completed by P in 1 day.
Remaining 4 units of work will be completed by Q in 1 day.
Therefore, Time taken to complete 60 units of work = 18+1+1 = 20 days.


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App