Question 51

Aadish can complete a work in 14 days. If he worked for 8 days, then what fraction of the work would be left?

Aadish can complete a work in 14 days. If he worked for 8 days.

fraction of the work done by him = $$\frac{8}{14}$$ = $$\frac{4}{7}$$

Fraction of the work would be left = $$1-\frac{4}{7}$$

= $$\frac{7-4}{7}$$

= $$\frac{3}{7}$$