Question 47

Rakesh can do a piece of work in 45 days and Manoj can do the same work in 90 days. Find the time required to complete the same work if they work on alternate days and Rakesh starts the work.

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

Join CAT 2026 course by 5-Time CAT 100%iler

Crack CAT 2026 & Other Exams with Cracku!

Ask AI

Ask our AI anything

AI can make mistakes. Please verify important information.