Join WhatsApp Icon CAT WhatsApp Group
Question 44

A is twice as efficient as B and takes 45 days less than B to complete a job. Find the number of days in which they can finish the job together.

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free