If 12 men or 9 women can do a piece of work in 36 days, then how many days will 16 men and 18 women take to finish the same work?
$$13\frac{1}{5}$$
$$12\frac{4}{5}$$
$$14\frac{3}{5}$$
$$10\frac{4}{5}$$