Question 41

Mohi and Suniti working separately can do a work in 12 and 15 days, respectively. Mohi starts the work and they work on alternate days. In how many days will the work be completed?


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App