Rahul can complete his work in 7 days and Raj can complete the work in 4 days. How many total days will they take to complete the work together?
$$\frac{14}{11}$$ days
$$\frac{15}{11}$$ days
$$\frac{28}{13}$$ days
$$\frac{28}{11}$$ days