14 workers working 16 hours per day can demolish a building in 81 days. In how many days 18 workers working 24 hours per day can demolish the same building?
54 days
42 days
70 days
30 days
Create a FREE account and get:
Functions, Graphs and Statistics
Profit, Loss and Interest
Averages Mixtures Alligations
Probability, Combinatorics
Time And Work
Linear Equations
Number Series
Remainders
Data Sufficiency
Arithmetic
Profit And Loss
Progressions and Series
Time Speed Distance
Coordinate Geometry
Averages, Ratio and Proportion
Simple Interest Compound Interest
Logarithms
Geometry
Number Systems
Averages
Quadratic Equations
Percentages
Mensuration
Venn Diagrams
Time, Distance and Work
Inequalities
Algebra
Logarithms, Surds and Indices
Login to your Cracku account.
Follow us on
Incase of any issue contact support@cracku.in
Boost your Prep!