Question 15

Some carpenters promised to do a job in 15 days but 3 of them were absent and remaining did the job in 20 days. What was the original number of carpenters?

Let original number of carpenters = $$x$$

Using, $$M_1D_1=M_2D_2$$

=> $$x\times15=(x-3)\times20$$

=> $$15x=20x-60$$

=> $$20x-15x=60$$

=> $$x=\frac{60}{5}=12$$

$$\therefore$$ Original number of carpenters = 12

=> Ans - (C)

Get AI Help

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

Join CAT 2026 course by 5-Time CAT 100%iler

Crack CAT 2026 & Other Exams with Cracku!

Ask AI

Ask our AI anything

AI can make mistakes. Please verify important information.