S, T and U together can complete a work in 30 days. If the ratio of efficiency of S, T and U is 20: 15: 12 respectively, then in how many days U alone can complete the same work?

Solution

Let efficiencies of S, T and U be $$20x,15x$$ and $$12x$$ units/day respectively.

S, T and U together can complete the work in 30 days

=> Total work to be done = $$30\times(20x+15x+12x)=1410x$$ units

$$\therefore$$ Time taken by U alone to complete the work = $$\frac{1410x}{12x}=\frac{235}{2}$$ days

=> Ans - (B)