Sign in
Please select an account to continue using cracku.in
↓ →
In a construction company the probability that the workers go on strike is 0.65 and the probability that a construction job will be completed on time if there is no strike is 0.80. If the probability that the construction job is completed on time even if there is strike is
0.32, then the probability that the construction job is completed on time is
Create a FREE account and get: