Question 126

Calculate the total correction (m) required, if a line measured using 20 m chain is 2380 m. Actual length of the chain is 20.2 m

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free