The following table refers to hotel construction projects. The cost of project increased at the rate of 10% per annum; if completed beyond 1997.

Question 112

Which of the following had the least cost per room ?

Cost per roomΒ :Β 

(A) : Raheja GroupΒ : $$\frac{250}{500}=0.5$$

(B) : Lokhandwala GroupΒ :Β $$\frac{225}{536}=0.41$$Β  Β  Β [MIN]

(C) : IHCL :Β $$\frac{275}{600}=0.45$$

(D) : ITC :Β $$\frac{300}{300}=1$$

=> Ans - (B)