Question 108

'x' number of men can finish a piece of work is 30 days. If there were 6 men more, the work culd be finished in 10 days less. The original number of men is

Solution

Let's say initial $$x$$ number of people were there, hence in a day efficiency of 1 man will be = $$\frac{1}{30x} $$
For $$x+6$$ same people efficiency of 1 man will be = $$\frac{1}{20(x+6)}$$
and both should be equal.
$$\frac{1}{30x} $$ = $$\frac{1}{20(x+6)}$$
after solving it, we will get $$x$$ = 12


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App