Question 101

A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. The number of days required for all the three put together to complete the work is


Create a FREE account and get:

  • Download Maths Shortcuts PDF
  • Get 300+ previous papers with solutions PDF
  • 500+ Online Tests for Free

cracku

Boost your Prep!

Download App