Sign in
Please select an account to continue using cracku.in
↓ →
A and B can complete a piece of work independently in 12 and 16 days respectively. Both of them start the work and after 4 day B leaves. In how many days, will A complete the work.
Create a FREE account and get:
Educational materials for CAT preparation
Ask our AI anything
AI can make mistakes. Please verify important information.
AI can make mistakes. Please verify important information.