A does 50% of a work in 12 days. He then calls in B and they together finish the remaining work in 8 days. How long B alone would take to complete the whole work?
Let total work to be done = 96 units
Work done by A in 12 days = $$\frac{50}{100} \times 96 = 48$$ units
A's efficiency = $$\frac{48}{12} = 4$$ units/day
Remaining work = 96 - 48 = 48 units
Let B's efficiency = $$x$$ units/day
Now, A and B complete remaining work in 8 days
=> $$(4 + x) \times 8 = 48$$
=> $$4 + x = \frac{48}{8} = 6$$
=> $$x = 6 - 4 = 2$$
$$\therefore$$ Time taken by B to complete the whole work alone = $$\frac{96}{2} = 48$$ days
=> Ans - (D)
Create a FREE account and get: