Question 8

Raman can do a piece of wo rk in 16 days. Satish can do the same work in 8 days wh ile Ashok can do it in 32 days. All of them wo rked togethe r when they started, but Satish left after 2 days. Raman left 3 days before the completion of wo rk. How lon g did it take to complete the entire work?