Question 78

20 men can do a piece of work in 10 days working 6 hours a day. How many men are needed to complete double the work in 8 days working 10 hours a day?


Create a FREE account and get:

  • Download Maths Shortcuts PDF
  • Get 300+ previous papers with solutions PDF
  • 500+ Online Tests for Free

cracku

Boost your Prep!

Download App