A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?
Let B's 1 day's work = $$2x$$ units/day
=> A's 1 day's work = $$1.5\times2x=3x$$ units/day
Let B takes $$d$$ days, => A takes $$(d-8)$$ days to finish the work.
=> Total work = $$2x\times d=3x\times(d-8)$$
=> $$2d=3d-24$$
=> $$d=24$$
$$\therefore$$ Total work = $$2x\times24=48x$$ units
If A and B work on alternate days and A works on first day, => Work done in 2 days = $$3+2=5$$ units
Multiplying both sides by 9, => Work done in 18 days = 45 units
Now, its A's turn to do the work, thus he will do the remaining 3 units on the 19th day.
=> Ans - (B)