Question 63

A, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining task is:

Let the total work be 240 units.

(LCM of 20, 16 and 30 is 240.)

Efficiency of A = total work/time taken to complete work = 240/20 = 12

Efficiency of B = 240/16 = 15

Efficiency of C = 240/30 = 8

Work done by A and B in 4 days = 4 $$\times (12 + 15) = 4 \times$$ 27 = 108 units

Remaining work = 240 -108 = 132 units

Time taken by C to complete remaining work = 132/8 = 16 $$\frac{4}{8}$$ = 16 $$\frac{1}{2}$$

Get AI Help

Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

Join CAT 2026 course by 5-Time CAT 100%iler

Crack CAT 2026 & Other Exams with Cracku!

Ask AI

Ask our AI anything

AI can make mistakes. Please verify important information.