Question 58

A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work, is:

Solution

Let the total work be 120 units.

$$(\because$$ LCM of 24, 15 and 12 is 120.)

Efficiency of A = work/time = 120/24 = 5 units/day
Efficiency of B = 120/15 = 8 units/day
Efficiency of C = 120/12 = 10 units/day
Work done by B and C in 3 days  = (8 + 10) $$\times 3 = 18 \times$$3 = 54 units

Remaining work = 120 - 54 = 66 units
Time taken by A to complete the remaining work = 66/5 = 13 $$\frac{1}{5}$$


Create a FREE account and get:

  • Free SSC Study Material - 18000 Questions
  • 230+ SSC previous papers with solutions PDF
  • 100+ SSC Online Tests for Free

cracku

Boost your Prep!

Download App