Shyam prepares and sells piping hot puri and sabji (gravy) from 7:00 am to 9:00 am (both inclusive) through a stall at XLRI campus. Presently, he has just a single oven, which can do only one job at a time. It takes 30 minutes to cook one handi (a large bowl) of sabji, sufficient for 12 customers. It takes him 10 minutes to prepare 2 plates of puri at a time. While the cost of a plate of puri-sabji is ₹ 10, the price is ₹ 25. Puri stays hot for only 5 minutes after preparation, while sabji stays hot for 30 minutes only. It takes 10 minutes to reheat the sabji which stays hot for another 30 minutes. If he brings a handi of hot sabji from home, the transport would cost him ₹ 50. It can also stay hot for 30 minutes excluding the transportation time. Currently, every 20 minutes five plates are ordered. All unsold quantities are distributed at cost after 9:30 am.
Shyam’s stall was becoming popular by the day. Now he gets 5 customers every 10 minutes. After buying a second oven, he employed a helping hand, Aman at ₹ 100 for two hours. Aman can cook one handi of sabji in 20 minutes or can prepare 3 plates of puri in 10 minutes. Reheat time for sabji is 10 minutes. None of them can work on both the ovens simultaneously.
Which of the following options will help Shyam maximize his daily profit, if he does NOT bring sabji from home?
Since the efficiency of Aman in making both Sabji and Puri is better than that of Shyam, Shyam should use his proficiencies in both parts.
For the first 20 minutes, Aman will make sabji and Shyam will make puri in the next 10 min. Then they can make puris in the ovens simultaneously and hence, can work on both the parts.
Thus, the correct answer is D.