64 men working 8 hours a day plan to complete a piece of work in 9 days. After 5 days, they were able to complete only 40% of the work. The number of hours they should work per day so as to complete the remaining work in 4 more days is
We know ,unit of work=M×D×H
M=number of men
H=number of hour
D=number of days.
if 64 men complete 40% of work in 5 days,
then work done=64×5×8=2560 unit.
so,40% work=2560 units.
so,60% work=2560(60/40)=3840 units.
let say, to complete the work in 4 days they need to work for x hour per day .
So,64×4×x=3840
or, x=15.
D is correct choice.