18 men and 12 women can complete a work in 18 days. A women takes twice as much time as a man to complete that work. Then the number of days required for 8 men to complete the same work is
18m+12w=>18days.
2w=1m.
18m+6m=>18days.
So,24 man can do the task in 18 days.
So,8men can do it in=(24×18)/8=54 days.
B is correct choice.