Last 6 Months to CAT 2024 🎉 Get upto 65% Off Today on CAT courses. Enroll now
A can do a piece of workin 40 days. He workedat it for 5 days and B finished the remaining work in 21 days. In how many days can A and B together finish the work?
13 days
15 days
6 $$\frac{2}{3}$$
18 $$\frac{1}{7}$$
Create a FREE account and get:
Charts
2D & 3D LR
Arrangement
Miscellaneous LR
Special Charts
Coins and Weights
Data Interpretation
DI with connected data sets
Maxima-Minima
Quant Based LR
Truth Lie Concept
Venn Diagrams
Selection With Condition
Routes And Networks
Scheduling
DI Miscellaneous
Games and Tournamnents
Table with Missing values
Data change over a period
Puzzles
Quant Based DI
Data Interpretation Basics
Login to your Cracku account.
Follow us on
Incase of any issue contact support@cracku.in
Boost your Prep!