Question 127

A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men were there in the beginning ?

Solution

Let there be m men originally to work in 60 days

If the men were m + 8, the work would be completed in 50 days.

(m+8)/m = 60/50

So, m = 40