Question 113

32 Men can complete a job in 16 days. In how many days will 16 men complete that job ?

Solution

32 men complete a job in 16 days.
The number of days it takes 1 man to complete the job is 32*16 = 512 days.

Hence, the number of days it takes 16 men to complete the job is 512/16 = 32 days.
As none of the options is 32 days, the correct answer is option (e)