Top CAT Quant Time and Work Questions PDF

by Naveen Neredimalli Wed 24 Apr 2024 05:15 PM 422
CAT_Quant_-_TIME_AND_WORK_-__Questions_With_Detailed_Solutions_

One of the most important parts of the CAT exam is the Quant section on time and work questions. This topic's questions continue to show up on the CAT exam each year. Practice is the key, keep taking mocks from the past CAT exams which will help you in gaining a fair idea about the exam. To help the aspirants ace this topic, we have provided you with the top 30+ Time and Work questions from CAT's previous papers with detailed video solutions, which are given below and also check out the free CAT mocks and understand the types of questions that are likely to appear on the exam. One can also download all the CAT past year Questions from TSD & work in PDF format along with the video solution for every question.

Download Time & Work Questions With Solutions PDF

Question 1

Ramesh and Ganesh can together complete a work in 16 days. After seven days of working together, Ramesh got sick and his efficiency fell by 30%. As a result, they completed the work in 17 days instead of 16 days. If Ganesh had worked alone after Ramesh got sick, in how many days would he have completed the remaining work?


Question 2

Anil alone can do a job in 20 days while Sunil alone can do it in 40 days. Anil starts the job, and after 3 days, Sunil joins him. Again, after a few more days, Bimal joins them and they together finish the job. If Bimal has done 10% of the job, then in how many days was the job done?


Question 3

At their usual efficiency levels, A and B together finish a task in 12 days. If A had worked half as efficiently as she usually does, and B had worked thrice as efficiently as he usually does, the task would have been completed in 9 days. How many days would A take to finish the task if she works alone at her usual efficiency?


Question 4

Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?


Question 5

X, Y, and Z are three software experts, who work on upgrading the software in a number of identical systems. X takes a day off after every 3 days of work, Y takes a day off after every 4 days of work and Z takes a day off after every 5 days of work.
Starting afresh after a common day off,
i) X and Y working together can complete one new upgrade job in 6 days
ii) Z and X working together can complete two new upgrade jobs in 8 days
iii) Y and Z working together can complete three new upgrade jobs in 12 days If X, Y and Z together start afresh on a new upgrade job (after a common day off), exactly how many days will be required to complete this job?

Show Answer Explanation

Question 6

A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?


Question 7

John takes twice as much time as Jack to finish a job. Jack and Jim together take one-thirds of the time to finish the job than John takes working alone. Moreover, in order to finish the job, John takes three days more than that taken by three of them working together. In how many days will Jim finish the job working alone?


Question 8

Anu, Vinu and Manu can complete a work alone in 15 days, 12 days and 20 days, respectively. Vinu works everyday. Anu works only on alternate days starting from the first day while Manu works only on alternate days starting from the second day. Then, the number of days needed to complete the work is


Question 9

Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is


Question 10

Anil can paint a house in 60 days while Bimal can paint it in 84 days. Anil starts painting and after 10 days, Bimal and Charu join him. Together, they complete the painting in 14 more days. If they are paid a total of ₹ 21000 for the job, then the share of Charu, in INR, proportionate to the work done by him, is


Question 11

Two pipes A and B are attached to an empty water tank. Pipe A fills the tank while pipe B drains it. If pipe A is opened at 2 pm and pipe B is opened at 3 pm, then the tank becomes full at 10 pm. Instead, if pipe A is opened at 2 pm and pipe B is opened at 4 pm, then the tank becomes full at 6 pm. If pipe B is not opened at all, then the time, in minutes, taken to fill the tank is


Question 12

One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is


Question 13

Anil can paint a house in 12 days while Barun can paint it in 16 days. Anil, Barun, and Chandu undertake to paint the house for ₹ 24000 and the three of them together complete the painting in 6 days. If Chandu is paid in proportion to the work done by him, then the amount in INR received by him is


Question 14

Working alone, the times taken by Anu, Tanu and Manu to complete any job are in the ratio 5 : 8 : 10. They accept a job which they can finish in 4 days if they all work together for 8 hours per day. However, Anu and Tanu work together for the first 6 days, working 6 hours 40 minutes per day. Then, the number of hours that Manu will take to complete the remaining job working alone is


Question 15

A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is


Question 16

Bob can finish a job in 40 days, if he works alone. Alex is twice as fast as Bob and thrice as fast as Cole in the same job. Suppose Alex and Bob work together on the first day, Bob and Cole work together on the second day, Cole and Alex work together on the third day, and then, they continue the work by repeating this three - day roster, with Alex and Bob working together on the fourth day, and so on. Then, the total number of days Alex would have worked when the job gets finished, is


Question 17

The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression. Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 days and 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number of days Sunil will take to finish the job working alone, is


Question 18

Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job. On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job. However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. If Rakshita had worked alone on the job then the number of days she would have taken to finish the job, cannot be


Question 19

Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is


Question 20

Pipes A and C are fill pipes while Pipe B is a drain pipe of a tank. Pipe B empties the full tank in one hour less than the time taken by Pipe A to fill the empty tank. When pipes A, B and C are turned on together, the empty tank is filled in two hours. If pipes B and C are turned on together when the tank is empty and Pipe B is turned off after one hour, then Pipe C takes another one hour and 15 minutes to fill the remaining tank. If Pipe A can fill the empty tank in less than five hours, then the time taken, in minutes, by Pipe C to fill the empty tank is

Related Articles

CAT Quant - Averages -  Questions With Detailed Solutions

Most Important CAT Averages Questions [PDF]

Read Blog
CAT - GEOMETRY TRIANGLES -  Questions With Detailed Solutions

Top 10 - CAT Geometry Triangles Questions [Download PDF]

Read Blog
CAT_Quant_-_Probability_and_Permutations__Combinations_-__Questions_With_Detailed_Solutions_

Top CAT Probability and Permutations & Combinations Questions PDF

Read Blog
CAT_Quant_-_Time_speed__Distance_-__Questions_With_Detailed_Solutions_

Top CAT Quant Time, Speed and Distance Questions PDF

Read Blog
how_to_analyze_mocks_

How to Analyze Mocks To Improve CAT Percentile? Check Now

Read Blog
CAT Admit Card

CAT Admit Card 2024, Download Hall Ticket at @iimcat.ac.in

Read Blog
How_to_Prepare_for_Quantitative_Aptitude_w1B0rlX

How to Prepare for Quantitative Aptitude for CAT 2024?

Read Blog
How_to_Manage_CAT_Preparation_with_College

How To Manage CAT Preparation With College?

Read Blog
CAT 2024

CAT 2024, Registration, Syllabus, Eligibility, Admit Card

Read Blog
Common_Mistakes_to_Avoid_During_CAT_Preparation

8 Common Mistakes to Avoid During CAT 2024 Preparation

Read Blog
CAT_2024_VARC_Preparation_Guide

How To Master CAT 2024 VARC ? Check Tips And Tricks Now

Read Blog
CAT Eligibility Criteria 2024

CAT Eligibility Criteria 2024, Reservation Criteria, Age Limit

Read Blog
cracku

Boost your Prep!

Download App