The following table refers to hotel construction projects. The cost of the project increased at the rate of 10% per annum; if completed beyond 1997.
For year 1998:
Total value = Bombay hotels + Lokhandwala group
Total value = 250 + 225 = 475
Required value = 10 % increase in total value
1.1 * 475 = 522.5