The following table refers to hotel construction projects. The cost of the project increased at the rate of 10% per annum; if completed beyond 1997.
What is the approximate cost incurred (in Rs. crore) for projects completed by 2000?
For year 1998:
Total value = 250 + 225 = 475Â
Required value = 1.1 * 475 = 522.5Â
For year 1999:
Total value = 275+235+250+300 = 1060
Required value = 1.1 * 1.1*1060 = 1282.6
For year 2000:
Total value = 250Â
Required value = 1.1 * 1.1*1.1*250 = 332.75
Total required value = 2137.85