Question 85

How many workers are required for completing the construction work in 10 days ?
A. 20% of the work can be completed by 8 workers in 8 days.
B. 20 workers can complete the work in 16 days.
C. One-eighth of the work can be completed by 8 workers in 5 days.

Solution

NOTE :- $$\frac{M1 * D1}{W1}$$ = $$\frac{M2 * D2}{W2}$$

where M-> no. of men

D-> no. of days

W-> no. of days


I : Let n workers are required to finish work in 10 days. Let work is 100 units. 20% of work is 20 units.

$$\frac{8*8}{20}$$ = $$\frac{10*n}{100}$$

=> n = 32.

Thus, I is sufficient.


II : Let work is 100 units.

$$\frac{20*16}{100}$$ = $$\frac{10*n}{100}$$

=> n = 32

Thus, II is sufficient.


III : Let work is 100 units. One eighth of work is 12.5 units.

$$\frac{8*5}{12.5}$$ = $$\frac{10*n}{100}$$

=> n = 32.

Thus, III is sufficient.


Ans - Any one of the three statements is sufficient.


Create a FREE account and get:

  • Banking Quant Shortcuts PDF
  • Free Banking Study Material - (15000 Questions)
  • 135+ Banking previous papers with solutions PDF
  • 100+ Online Tests for Free

cracku

Boost your Prep!

Download App