A company manufactures two products X and Y. One unit of X requires three units of material A and two units of material B while one unit of Y requires two units of material A and five units of material B. If 25 units of each product were to be produced, calculate the requirement of material B. If 25 units of each product were to be produced calculate the requirement of material B.
One unit of X requires two units of material B, then 25 unit of X will require = 2 * 25 = 50 units of material B
One unit of Y requires five units of material B, then 25 unit of Y will require = 5 * 25 = 125 units of material B
Total requirement of material B = 50 + 125 = 175