A alone can do a piece of work in 12 days. B alone can do the same work in 18 days. C alone can do the same work in 24 days. In how many days will they complete 65% of the work, if all three work together?
Let's assume the total work is 72 units.
A alone can do a piece of work in 12 days.
Efficiency of A =Â $$\frac{72}{12}$$ = 6 units/day
B alone can do the same work in 18 days.
Efficiency of B = $$\frac{72}{18}$$ = 4 units/day
C alone can do the same work in 24 days.
Efficiency of C = $$\frac{72}{24}$$ = 3 units/day
Time taken by all three working together to complete 65% of the work = 65% of $$\frac{72}{\left(6+4+3\right)}$$
= 65% of $$\frac{72}{13}$$
=Â $$\frac{65}{100}\times\frac{72}{13}$$
= $$\frac{5}{100}\times72$$
= $$\frac{360}{100}$$
=Â 3.6 days
Create a FREE account and get: