50 men can complete a work in 28 days. They started the work together, but at the end of each $$10^{th}$$ day, 10 men left the job. The work was completed in how many days?
Let a man can do 1 unit/day
=> Total work = $$50\times28=1400$$ man days
So, work done in first 10 days by 50 men = $$10\times50=500$$ man days
Then, work done in next 10 days by 40 men =Â $$10\times40=400$$ man days
Similarly, 300 man days after next 10 days and 200 after that.
Thus, $$500+400+300+200=1400$$ man days
=> Total days required = 40 days
=> Ans - (C)