Sanda and Mayuri can complete a task in 45 days by working together. However, Mayuri works alone and leaves one-third of the work, and then Sandra completes the rest on her own. This allows them to complete the task in 104 days. If Mayuri did the job faster than Sando, how long would it take Sander alone to get the job done?