Akash, Bhanu and Sam work on a project. After they complete 1/4th of the project, Sam takes a break For 7 days only Akash and Bhanu work on the project. After that Sam relieves both of them. He completes the project in five more days. Bhanu works 50% faster than Akash and Sam alone can finish the entire project in 20 days. How long would Bhanu take to finish the entire project? a) 25 days D) 23 1/3 days c) 21 days d) 22 1/2 days