Edit MetaData
4 years, 7 months ago
A, B and C can complete a work in 20, 24 and 30 days respec tively. All of them starts to gether but after 4 days A leaves the job and B left the job 6 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?
4 years, 7 months ago
Take LCM of their respective days as total work.
implies 20,24,30's LCM Is 120..
(As we know the efficiency is total work divided by no:of days of work),
efficiency of A is 6, B's efficiency 5 and C's 4.
As per the qn, all of three together works for 4 days,after that A leaves. So 3 of them works for 4 days completing 60 works out of 120.( efficiency of A+B+C=15. 15×4days=60)
B leaves the job 6 days before completing, that means only C works for last 6 days
that is 4×6 days =24 unit work of 120
so total 60+24= 84 units of work is completed
The rest 36 units work is done by both B AND C.
36÷9=4 DAYS
SO TOTAL DAYS IS 4+6+4= 14 DAYS
(Never bother about lengthy description.The method is soo simple.There is no option to attach image other wise I would have done it)
4 years, 7 months ago
Total work = LCM(20,24,30) = 120 units
A @ 6units/day
B @ 5 un/day
C @ 4un/day
Let's say the total work i.e. 120units is completed in x days.
A worked for 4 days = 6*4 = 24units by A
B worked for x-6 days
C worked for all the days
==> work done by A+B+C = 120
==> 24+5(x-6)+4x = 120
==> 24+5x-30+4x = 120
==> 9x = 126
==> x = 14 days