The steps involved in project approval are as follows:
A. Carrying out a detailed project analysis
B. Developing infrastructure prototype for project development
C. Generating a business idea
D. Performing a project specific factor analysis
E. Conducting a free-feasibility analysis
Choose the most appropriate answer from the options given below that shows right sequence
The correct order of sequence is:
C. Generating a business idea
D. Performing a project-specific factor analysis
E. Conducting a pre-feasibility analysis
A. Carrying out a detailed project analysis
B. Developing an infrastructure prototype for project development
In this sequence, the project approval process starts with generating a business idea. Then, a project-specific factor analysis is performed to assess the various factors and considerations specific to the project. Next, a pre-feasibility analysis is conducted to evaluate the feasibility and viability of the project. After that, a detailed project analysis is carried out, taking into account all relevant aspects of the project. Finally, an infrastructure prototype is developed for project development.
Therefore, the correct sequence is CDEAB.
Create a FREE account and get:
CMAT Economic and Social Issues
CMAT Innovation and Entrepreneurship
CMAT Data Interpretation Basics
CMAT Indian National Static GK
CMAT Grammar and Sentence Correction
CMAT Logarithms, Surds and Indices
CMAT Functions, Graphs and Statistics
CMAT Banking Computer Knowledge
CMAT Probability, Combinatorics
Educational materials for CAT preparation