A group of workers could complete a piece of work in 84 days. If there were 6 more workers, it would have taken 12 days less to finish the same piece of work. What was the actual strength of workers ?
Using : $$M_1 D_1 = M_2 D_2$$
Let $$x$$ men finish the work in 84 days
=> $$(x + 6)$$ workers finish the work in 72 days
=> $$M_1 = x , D_1 = 84$$ and $$D_2 = 72$$
=> $$x \times 84 = (x + 6) \times 72$$
=> $$x \times 7 = (x + 6) \times 6$$
=> $$7x = 6x + 36$$
=> $$7x - 6x = x = 36$$