A, B and C can complete a work alone in 400, 600 and 900 days respectively. In how many days can the work be completed if it is started by A and he is assisted by B and C on every second and third day respectively?
A, B and C can complete a work alone in 400, 600 and 900 days respectively.
LCM of 400, 600 and 900 is 3600 which can be assumed as the total work.
Efficiency of A =Â $$\frac{3600}{400}$$ = 9 units/day
Efficiency of B =Â $$\frac{3600}{600}$$ = 6 units/day
Efficiency of C =Â $$\frac{3600}{900}$$ = 4 units/day
if it is started by A and he is assisted by B and C on every second and third day respectively?
FIrst day + second day + third day =Â Efficiency of A + (Efficiency of A+Efficiency of B) + (Efficiency of A+Efficiency of C)
= 9 + (9+6) + (9+4)
= 9 + 15 + 13
= 37
In three days 37 units is done.
$$3\times97$$ days =Â $$37\times97$$Â units
291 days =Â 3589 units
Now 11 units of work is remaining. So on 292nd day 9 units will be completed and the remaining 2 units will be completed in $$\frac{2}{15}\ days$$.Â
Number of days required to complete the whole work as per the given condition =Â $$291+1+\frac{2}{15}$$
=Â $$292+\frac{2}{15}$$
=Â 292.13
= 292 days (approx.)
Create a FREE account and get: